24-03-2015, last updated 25-03-2015 8:52
July 31 city extended the deadline for submission of bids by companies wishing to build another station the second metro line. Originally, the term passed March 31.
The author: Robert Gardziński
Source: Fotorzepa
– We passed the deadline for submission of tenders to 31 July in connection with the fact that a letter received requests from contractors for an extension of the term – Capital Metro spokeswoman Anna Bartoń.
She said that in connection with the tender attracted to the Warsaw Metro over 1,300 questions, which the company must respond. Warsaw announced a tender for the construction of new underground railway stations – three on the east and west of the central section – in October 2014.
Each company will be able to submit a tender for the construction of only one section. Determined at the time that the company will be able to submit their bids by 31 March of 2015.
In the west (from Ronda Daszyńskiego) will be built approx. 3,4 km underground railway. Planned stops include: “Wolska” (at ul. Plock at the intersection of ul. Wolska), “Moczydło” (at ul. Górczewska the eastern side of the railway viaduct in the area of. Sokołowska and sirens) and “Prince Janusz” (at ul. Górczewska in the area of the intersection of the street. Prince Janusz).
In the north-east (the Vilnius Railway Station) creation of approx. 3.12 km new route, and at the stations, “Swedish” (at ul. arms, on the east side of the street. Steel), “Targowek 1″ (near the intersection. Pratulińskiej with Ossowski) and “Targowek 2″ (in the area of the intersection. Pratulińskiej of Trocka).
The second metro line with six new stations will have a length of over 13.5 km. According to the tender documents the construction of new stations should take no longer than 38 months.
During the announcement of the tender Metro president Jerzy Lejk said that “if one could sign a contract in mid-2015., In 2018, the first half of 2019 r., if all that well ran, should be ready this building. ” Bartoń said that “the estimated time” remains unchanged this time.
PAP
No part or whole songs contained in the log can not be reproduced or further distributed in any form or by any means (including electronic, mechanical or otherwise, or for any field of use) including copying, the wider digitization, photocopying or copying, including clearance for Internet – without the written permission of Gremi Business Communication Sp. with o.o
Any use or the use of songs in whole or in part without permission Gremi Business Communication Sp. with o.o or authors of the violation of law is forbidden under threat of punishment and can be prosecuted.
No comments:
Post a Comment